[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49751":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},49751,53,1,"单选题","下列各选项中，()不是依次施工组织方式的特点。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工现场组织管理比较复杂",true,{"key":16,"text":17,"correct":18},"B","单位时间内投入的资源量较少",false,{"key":20,"text":21,"correct":18},"C","没有充分利用工作面，工期拖得较长",{"key":23,"text":24,"correct":18},"D","各专业工作队的工人和专业工人出现间歇，不能连续生产作业","依次施工组织方式的特点： 1）单位时间内投入的资源量较少；2）施工现场组织管理比较简单；3）没有充分利用工作面，工期拖得较长；4）各专业工作队的工人和专业工人出现间歇，不能连续生产作业；5）不能实现专业化分工，不利于提高劳动生产率。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]