[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49748":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},49748,53,1,"单选题","组织一项成倍节拍流水施工，各施工过程的流水节拍分别为t1=2天，t2=4天，t3=6天，则第2个施工过程的专业工作队数为()队。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","3",{"key":19,"text":20,"correct":21},"C","2",true,{"key":23,"text":24,"correct":14},"D","4","计算步骤如下：①流水节拍的最大公约数，即K=2；②确定各施工过程的专业工作队数为：2\u002F2=1（队）；4\u002F2=2(队)；6\u002F2=3(队)。所以第2个施工队的专业工作队数为2队。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]