[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49744":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},49744,53,1,"单选题","工程项目前期工作计划的编制是在()进行的。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目的初步设计被批准后",false,{"key":16,"text":17,"correct":14},"B","编制项目设计任务书的同时",{"key":19,"text":20,"correct":14},"C","项目的可行性研究被批准后",{"key":22,"text":23,"correct":24},"D","项目预测的基础上",true,"工程项目总进度计划，是指在工程项目的初步设计被批准后编制。工程项目前期工作计划应根据工程特点、建设规模和总进度目标等进行编制，它主要包括项目可行性研究、设计任务书及初步设计的工作进度安排。通过该项计划，使建设前期的各项工作相互衔接，时间得到控制。前期工作计划一般由建设单位在预测的基础上进行编制。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]