[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49741":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},49741,53,1,"单选题","关于工程进度管理的说法，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程进度管理的目的是使工程总成本最低",false,{"key":16,"text":17,"correct":14},"B","工程进度管理的目的是使工程建设周期最短",{"key":19,"text":20,"correct":14},"C","通过进度管理可使工程项目的各项目标均达到最优",{"key":22,"text":23,"correct":24},"D","工程进度管理的目的是确保项目工期目标的实现",true,"本题考核的是工程进度计划的作用。通过进度管理可以将项目的计划工期控制在事先确定的目标工期范围内，在兼顾工程成本目标、质量目标的同时，努力缩短建设工期。通过进度管理，要实现成本目标、工期目标、质量目标，但目标并不是工期最短、质量最高、成本最低，而且这三个目标之间是对立统一的。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]