[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49739":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},49739,53,1,"单选题","采用横道图编制工程进度计划的不足是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","编制较为复杂、繁琐",false,{"key":16,"text":17,"correct":14},"B","由于人们不太熟悉，所以在进度管理中不常用",{"key":19,"text":20,"correct":14},"C","计算劳动力和资源消耗量较为困难",{"key":22,"text":23,"correct":24},"D","不能反映工作之间相互联系、相互制约的关系",true,"采用横道图编制工程进度计划的不足是不能反映工作之间相互联系、相互制约的关系。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]