[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49736":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},49736,53,1,"单选题","编制工程项目进度计划的工作包括：①确定进度目标；②确定工作持续时间；③划分工作过程；④编制初始进度计划；⑤检查是否满足要求；⑥计算各工作工程量；⑦进度计划调整、优化；⑧编制正式进度计划，上述各工作正确的步骤是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①一②一③一④一⑤一⑥一⑦一⑧",false,{"key":16,"text":17,"correct":18},"B","①一③一⑥一②一④一⑤一⑦一⑧",true,{"key":20,"text":21,"correct":14},"C","①一⑥一②一③一④一⑤一⑦一⑧",{"key":23,"text":24,"correct":14},"D","①一③一②一⑥一④一⑤一⑦一⑧","工程进度计划的编制步骤是：确定进度目标-划分工作过程-计算各工作工程量-确定工作持续时间-编制初始进度计划-检查是否满足要求-进度计划调整、优化-编制正式进度计划。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]