[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49734":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},49734,53,1,"单选题","下列有关工程进度管理说法，正确的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","进行工程进度管理的目的是使工程建设周期最短",false,{"key":16,"text":17,"correct":14},"B","通过工程进度管理可使工程总投资最省",{"key":19,"text":20,"correct":21},"C","工程进度管理的目的是确保工程进度总目标的实现",true,{"key":23,"text":24,"correct":14},"D","通过进度管理可使工程项目的各项目标均达到最优","工程进度管理是指在工程项目实施过程中，对各阶段的进展程度和工程项目最终完成的期限所进行的管理，其目的是保证工程项目在满足时间约束条件的前提下实现其总目标。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]