[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49729":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},49729,53,1,"单选题","工程进度计划执行信息的主要来源是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","进度计划执行情况的跟踪检查",true,{"key":16,"text":17,"correct":18},"B","监理工程师的工作指令",false,{"key":20,"text":21,"correct":18},"C","项目经理的施工命令",{"key":23,"text":24,"correct":18},"D","实际进度的数据与计划进度的数据进行比较","本题考查的是工程进度计划的实施与检查。 对进度计划的执行情况进行跟踪检查是计划执行信息的主要来源，是进度分析和调整的依据，亦是进度控制的关键步骤。 其余选项为混淆选项。 故本题正确答案为A。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]