[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49704":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},49704,53,1,"单选题","组织分别流水施工的关键是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","确定流水节拍",false,{"key":16,"text":17,"correct":14},"B","确定技术间歇时间",{"key":19,"text":20,"correct":21},"C","确定相邻两个专业工作队之间的流水步距",true,{"key":23,"text":24,"correct":14},"D","确定流水施工工期","本题考查的是分别流水施工。 组织分别流水施工的关键是确定各施工过程相邻两个专业工作队之间的流水步距，使其在开工时间上能够最大限度地搭接起来。 其余选项为混淆选项。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]