[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49643":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},49643,53,1,"单选题","供货方的项目管理工作主要在()阶段。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计前准备",false,{"key":16,"text":17,"correct":18},"B","施工",true,{"key":20,"text":21,"correct":14},"C","设计",{"key":23,"text":24,"correct":14},"D","动用前准备","供货方的项目管理工作主要在施工阶段进行，但它也涉及设计前准备阶段、设计阶段、动用前准备阶段和保修期。供货方项目管理的任务包括供货的安全管理；供货方的成本控制；供货的进度控制；供货的质量控制；供货合同管理；供货信息管理；与供货有关的组织与协调。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]