[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49631":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},49631,53,1,"单选题","()是项目建设的最后一个程序。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设项目质量控制",false,{"key":16,"text":17,"correct":14},"B","可行性研究",{"key":19,"text":20,"correct":14},"C","投资效益评价",{"key":22,"text":23,"correct":24},"D","建设项目竣工验收",true,"建设项目竣工验收是建设项目建设全过程的最后一个程序，是全面考核建设工作，检查设计、施工质量是否符合要求，审查投资使用是否合理的重要环节。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]