[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49610":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},49610,53,1,"单选题","我国建设项目的设计一般分为()两个阶段。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","总体规划设计和施工图设计",false,{"key":16,"text":17,"correct":14},"B","技术设计和施工图设计",{"key":19,"text":20,"correct":21},"C","初步设计和施工图设计",true,{"key":23,"text":24,"correct":14},"D","初步设计和技术设计","在我国，建设项目的设计一般分为两个阶段设计，即初步设计阶段和施工图设计阶段。对于特大规模的建设项目，或工艺极为复杂，或采用新工艺、新设备、新技术而且有待试验研究的新开发项目，某些援外项目及极为特殊的项目，经上级机关或主管部门批准在初步设计批准后进行技术设计。对于一些特殊的大型工程，必要时增加总体规划设计，作为初步设计的依据。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]