[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49603":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},49603,53,1,"单选题","建设项目的交工验收是指（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","分部工程验收",false,{"key":16,"text":17,"correct":14},"B","分项工程验收",{"key":19,"text":20,"correct":21},"C","单位工程验收",true,{"key":23,"text":24,"correct":14},"D","单项工程验收","按被验收的对象划分，工程验收可分为单项工程验收、单位工程验收（称为“交工验收”）和工程整体验收（称为“动用验收”），通常所说的竣工验收指的是动用验收。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]