[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49582":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},49582,53,1,"单选题","下列关于工程分包合同签订的说法中，正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程分包合同均由业主负责签订",false,{"key":16,"text":17,"correct":18},"B","施工总承包单位与工程分包单位直接签订合同",true,{"key":20,"text":21,"correct":14},"C","工程监理单位与工程分包单位直接签订合同",{"key":23,"text":24,"correct":14},"D","工程造价咨询公司与工程分包单位签订合同","施工总承包管理模式的合同关系有两种可能，即业主与分包单位直接签订合同或者由施工总承包管理单位与分包单位签订合同。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]