[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49569":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},49569,53,1,"单选题","下列监理工作任务中，属于施工阶段质量控制主要任务的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","审查施工单位选择分包单位的资质",false,{"key":16,"text":17,"correct":14},"B","审核施工单位申报的月度和季度计量表",{"key":19,"text":20,"correct":14},"C","监督施工单位严格按照施工合同规定的工期组织施工",{"key":22,"text":23,"correct":24},"D","对隐蔽工程在隐蔽前进行检查和签证",true,"ABC从字面上理解就不是在说质量问题，A是施工准备阶段建设监理的主要任务；BC是指施工阶段的进度控制。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]