[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49551":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},49551,53,1,"单选题","一个工程项目必须在一个()范围内，由一个或若干个互有内在联系的单项工程所组成。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目建议书批复",false,{"key":16,"text":17,"correct":14},"B","项目可行性研究批复",{"key":19,"text":20,"correct":21},"C","总体设计或初步设计",true,{"key":23,"text":24,"correct":14},"D","承包合同","凡属于一个总体设计或初步设计的项目，不论是主体工程还是相应的附属配套工程，不论是由一个还是由几个施工单位施工，不论是同期建设还是分期建设，都视为一个工程项目。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]