[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49540":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},49540,53,1,"单选题","在我国的建设程序中，项目的设计、施工，直至项目交付使用称为()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目动用(使用)阶段",false,{"key":16,"text":17,"correct":14},"B","项目全寿命周期",{"key":19,"text":20,"correct":21},"C","项目实施阶段",true,{"key":23,"text":24,"correct":14},"D","项目决策阶段","自项目的开始至项目的完成指的是项目的实施阶段。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]