[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49519":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},49519,53,1,"单选题","控制工程项目目标最重要的措施是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","经济措施",false,{"key":16,"text":17,"correct":14},"B","技术措施",{"key":19,"text":20,"correct":21},"C","组织措施",true,{"key":23,"text":24,"correct":14},"D","协调措施","控制项目目标的主要措施包括组织措施、管理措施、经济措施和技术措施，其中组织措施是最重要的措施。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]