[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49512":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},49512,53,1,"单选题","下列工作中，建设单位在编制设计任务书之前应完成的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","拆迁",false,{"key":16,"text":17,"correct":18},"B","建设项目可行性研究",true,{"key":20,"text":21,"correct":14},"C","指定投资计划",{"key":23,"text":24,"correct":14},"D","选择建筑师","设计前准备阶段的投资控制工作内容有：建设单位在可行性研究的基础上，进行项目总投资目标的分析和论证；编制项目总投资分解的初步规划；编写设计任务书中有关投资控制的内容；对设计方案提出投资评价建议；根据选定的设计方案审核项目总投资估算；编制设计阶段资金使用计划，并控制其执行；编制投资控制报表和报告。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]