[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49490":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},49490,53,1,"单选题","施工项目的控制目标不包括( )目标。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","人员控制",true,{"key":16,"text":17,"correct":18},"B","进度控制",false,{"key":20,"text":21,"correct":18},"C","质量控制",{"key":23,"text":24,"correct":18},"D","成本控制","本题考查的是施工阶段施工方项目管理任务。 施工方项目管理的任务包括：①施工安全管理；②施工成本控制；③施工进度控制；④施工质量控制；⑤施工合同管理；⑥施工信息管理；⑦与施工有关的组织与协调。 其余选项为混淆选项。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]