[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49480":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},49480,53,1,"单选题","下列不属于项目经理方面内容的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工安全管理",false,{"key":16,"text":17,"correct":14},"B","施工成本控制",{"key":19,"text":20,"correct":14},"C","施工进度控制",{"key":22,"text":23,"correct":24},"D","施工招标管理",true,"本题考查的是施工企业项目经理。 项目经理的任务包括项目的行政管理和项目管理两个方面，其在项目管理方面的主要任务是施工安全管理、施工成本控制、施工进度控制、施工质量控制、工程合同管理、工程信息管理、工程组织与协调等。 其余选项为混淆选项。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]