[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-49451":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},49451,53,1,"单选题","一个工程项目往往是由多个相互关联的子项目构成的系统，其中一个子项目的失败有可能影响整个项目的功能的实现。这说明工程项目具有( )的特点。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","整体性",true,{"key":16,"text":17,"correct":18},"B","唯一性",false,{"key":20,"text":21,"correct":18},"C","单件性",{"key":23,"text":24,"correct":18},"D","复杂性","本题考查的是工程项目的特点. 建设产品具有整体性的特点，项目建设包括多个阶段，各阶段有着紧密的联系，各阶段的工作都对整个项目的完成产生影响，题中的描述说明工程项目具有整体性的特点。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]