[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-47920":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},47920,53,1,"单选题","某工程项目分解为基础工程、主体工程、层面工程、装饰工程四个施工过程，划分为四个施工段组织流水作业，每一施工过程由一个专业工作队负责施工。各施工过程在各个施工段上的流水节拍如下表所示。 该工程项目各相邻施工过程之间的流水步距分别为( )个月。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3. 6. 3",true,{"key":16,"text":17,"correct":18},"B","3. 5. 4",false,{"key":20,"text":21,"correct":18},"C","4. 5. 3",{"key":23,"text":24,"correct":18},"D","4. 6. 5","采用最简便、易掌握的“潘特考夫斯基法”来确定相邻专业工作队之间的流水步距，其步骤如下：①累加各施工过程的流水节拍，形成累加数据系列。 ②将相邻两个施工过程的累加数据系列错位相减，得一系列差值。基础工程与主体工程： ③取差值中的最大者作为该两个相邻施工过程之间的流水步距(，i+l)，基础工程与主 体工程K=3，主体工程与层面工程K=6，层面工程与装饰工程K=3。 @##",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]