[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-47917":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},47917,53,1,"单选题","某基础工程包括开挖、支模、浇筑混凝土及回填四个施工过程，分3个施工段组织流水施工，流水节拍见下表，则该基础工程的流水施工工期为（）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","22",false,{"key":16,"text":17,"correct":18},"B","23",true,{"key":20,"text":21,"correct":14},"C","24",{"key":23,"text":24,"correct":14},"D","25","本题考查的是流水工期的确定。先用“累加数列错位相减取大差法”求流水歩距： 计算流水工期T=（6+4+2）+（4+4+3）=23天。 @##",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]