[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-47908":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},47908,53,2,"多选题","某工程项目分解为基础工程、主体工程、层面工程、装饰工程四个施工过程，划分为四个施工段组织流水作业，每一施工过程由一个专业工作队负责施工。各施工过程在各个施工段上的流水节拍如下表所示。 该工程项目的流水施工工期为( )个月。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","22",false,{"key":16,"text":17,"correct":14},"B","24",{"key":19,"text":20,"correct":21},"C","26",true,{"key":23,"text":24,"correct":14},"D","28","@##",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]