[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-47891":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},47891,53,2,"多选题","某工程项目分解为基础工程、主体工程、屋面工程、装饰工程四个施工过程，划分为四个施工段组织流水作业，每一施工过程由一个专业工作队负责施工。各施工过程在各个施工段上的流水节拍如下表所示 回答72-75题; 根据该工程项目各施工过程时间参数的特征，下列关于该工程项目流水施工的说法中，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","该工程项目适宜采用分别流水组织施工",true,{"key":16,"text":17,"correct":18},"B","该工程项目适宜采用成倍节拍组织流水施工",false,{"key":20,"text":21,"correct":14},"C","组织该工程项目流水施工应使相邻专业工作队在开工时间上最大限度地搭接",{"key":23,"text":24,"correct":14},"D","组织该工程项目流水施工的关键问题是确定相邻专业工作队之间的流水步距","ACD","考核第四章第三节流水施工的基本组织方式。",{"id":6,"name":28,"category":29,"favorite":30},"(初级)建筑与房地产经济","经济金融",0]