[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-47878":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},47878,53,1,"单选题","某基础工程可划分为基坑开挖、混凝土垫层、砌基础、回填土四个施工过程。在施工中分三个施工段组织流水作业，各个施工过程在各流水段上的流水节拍如下表所示： 回答53-56题: 该基础工程适合采用的流水施工方式为( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","全等节拍流水施工",false,{"key":16,"text":17,"correct":14},"B","成倍节拍流水施工",{"key":19,"text":20,"correct":21},"C","分别流水施工",true,{"key":23,"text":24,"correct":14},"D","固定节拍流水施工","考核分别流水施工。分别流水施工是指参加流水作业的各施工过程在各施工段上的流水节拍无特定规律的流水施工组织方式。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)建筑与房地产经济","经济金融",0]