[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-851116":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},851116,528,1,"单选题","锅炉膨胀指示的检查，应在（ ）开始进行。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","上水时",true,{"key":16,"text":17,"correct":18},"B","点火时",false,{"key":20,"text":21,"correct":18},"C","投入煤粉后",{"key":23,"text":24,"correct":18},"D","达到额定负荷时","",{"id":6,"name":27,"category":28,"favorite":29},"(G2)电站锅炉司炉","特种作业",0]