[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-834824":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},834824,521,2,"多选题","在估算投资项目的相关现金流量时，下列各项中，不计入现金流出量的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","沉没成本",true,{"key":16,"text":17,"correct":18},"B","机会成本",false,{"key":20,"text":21,"correct":18},"C","付现成本",{"key":23,"text":24,"correct":14},"D","利息费用",{"key":26,"text":27,"correct":18},"E","营运资金垫支","AD","沉没成本是决策时点前已经发生的成本，不因为接受或拒绝某个项目而改变，因此是无关成本，不构成项目的现金流量，选项A是答案；利息费用和其他融资成本在项目投资决策中为了避免重复计算，不单独在项目的增量现金流量中考虑。因为无论是投资者投入还是借款获取的资金，在投资使用时，已经作为建设期现金流量考虑了；项目要求收益率对项目增量现金流量进行折现时，已经扣除了该项目的融资成本。选项D是答案。",{"id":6,"name":31,"category":32,"favorite":33},"资产评估相关知识","会计财税",0]