[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-832693":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},832693,521,2,"多选题","企业确定合同的完工进度可以选用的方法有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","累计实际发生的合同成本占合同预计总成本的比例",true,{"key":16,"text":17,"correct":14},"B","已经完成的合同工作量占合同预计总工作量的比例",{"key":19,"text":20,"correct":14},"C","实际测定的完工进度",{"key":22,"text":23,"correct":24},"D","估计的完工进度",false,{"key":26,"text":27,"correct":24},"E","累计实际发生的合同收入占合同预计总收入的比例","ABC","确定合同完工进度可以选用以下方法：（1）累积实际发生的合同成本占合同预计总成本的比例；（2）已经完成的合同工作量占合同预计总工作量的比例；（3）实际测定的完工进度。",{"id":6,"name":31,"category":32,"favorite":33},"资产评估相关知识","会计财税",0]