[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-832380":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},832380,521,1,"单选题","下列以出包方式形成的固定资产的说法中，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设期间发生的联合试车费计入管理费用",false,{"key":16,"text":17,"correct":14},"B","建设期间发生的工程物资盘亏.毁损.报废的净损失计入营业外支出",{"key":19,"text":20,"correct":14},"C","企业为建造固定资产通过出让方式取得土地使用权支付的土地出让金计入在建工程",{"key":22,"text":23,"correct":24},"D","企业为建造该固定资产结算的工程价款计入在建工程",true,"建设期间的工程物资盘亏、报废及毁损净损失以及联合试车费等计入待摊支出，所以选项AB是错误的；企业为建造固定资产通过出让方式取得土地使用权支付的土地出让金不作为在建工程成本，而是作为无形资产单独核算，所以选项C错误。",{"id":6,"name":27,"category":28,"favorite":29},"资产评估相关知识","会计财税",0]