[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-44029":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},44029,52,1,"单选题","某企业的单对象流水线计划日生产量为99件，每日工作8小时，时间有效利用系数为0.95，预计废品率为1%，则该流水线的平均节拍是（ ）分钟。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3.18",false,{"key":16,"text":17,"correct":14},"B","3.56",{"key":19,"text":20,"correct":21},"C","4.56",true,{"key":23,"text":24,"correct":14},"D","5.12","本题考查计算流水线的节拍。r＝βT0\u002FQ＝（0.95×8×60）÷（99÷99%）＝4.56（分钟）。",{"id":6,"name":27,"category":28,"favorite":29},"(初级)工商管理","经济金融",0]