[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-44015":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},44015,52,1,"单选题","某零件批量为n=3件，加工工序m=4，每道工序加工时间为t1=10分钟，t2=5分钟，t3=20分钟t4=10分钟，按平行移动方式计算生产周期为（ ）。\" >某零件批量为n=3件，加工工序m=4，每道工序加工时间为t1=10分钟，t2=5分钟，t3=20分钟t4=10分钟，按平行移动方式计算生产周期为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","135",false,{"key":16,"text":17,"correct":14},"B","95",{"key":19,"text":20,"correct":21},"C","85",true,{"key":23,"text":24,"correct":14},"D","120","",{"id":6,"name":27,"category":28,"favorite":29},"(初级)工商管理","经济金融",0]