[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-829589":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},829589,519,2,"多选题","PPP项目各阶段的资产评估需求，主要表现在下列（ ）方面。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","存量公共服务项目转型为政府和社会资本合作项目时",false,{"key":16,"text":17,"correct":18},"B","项目公司融资时",true,{"key":20,"text":21,"correct":18},"C","政府配套投入时",{"key":23,"text":24,"correct":18},"D","项目公司产权转让或资产转让时",{"key":26,"text":27,"correct":18},"E","项目资产移交时","BCDE","选项A，属于PPP存量项目的资产评估需求。",{"id":6,"name":31,"category":32,"favorite":33},"资产评估实务一","会计财税",0]