[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-829045":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},829045,519,1,"单选题","使用成本法进行房地合估时，下列选项不属于开发成本的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","勘察设计和前期工程费",false,{"key":16,"text":17,"correct":14},"B","基础设施建设费",{"key":19,"text":20,"correct":14},"C","房屋建筑安装工程费",{"key":22,"text":23,"correct":24},"D","土地取得成本",true,"开发成本主要由五个方面构成：（1）勘察设计和前期工程费；（2）基础设施建 设费；（3）房屋建筑安装工程费；（4）公共配套设施建设费；（5）开发期间税费指政府或其他部 门收取的费用。",{"id":6,"name":27,"category":28,"favorite":29},"资产评估实务一","会计财税",0]