[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-828911":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},828911,519,1,"单选题","为了分析设备的时间利用情况，对设备时间的划分不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","制度时间",false,{"key":16,"text":17,"correct":18},"B","休息时间",true,{"key":20,"text":21,"correct":14},"C","实际工作时间",{"key":23,"text":24,"correct":14},"D","计划工作时间","设备时间的利用好坏将直接影响生产能力的发挥，从而影响设备的效率。为了分 析设备的时间利用情况，可对设备时间做如下划分：日历时间、制度时间、计划工作时间、实际工作时间。",{"id":6,"name":27,"category":28,"favorite":29},"资产评估实务一","会计财税",0]