[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-826799":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},826799,519,1,"单选题","某企业生产成品实有数量为1500件，合理材料工艺定额为600公斤\u002F件，合理工时定额为20小时\u002F件。因为评估基准日与产成品完工时间间隔较长，评估时，生产该产品的材料价格由原来的50元\u002F公斤涨至60元\u002F公斤，单位小时合理工资工时、费用也由15元\u002F小时涨至20元\u002F小时。采用成本法估计时，该企业产成品评估值为()万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5460",true,{"key":16,"text":17,"correct":18},"B","4545",false,{"key":20,"text":21,"correct":18},"C","5445",{"key":23,"text":24,"correct":18},"D","4560","产成品评估值=1500×(600×60+20×20)=5460(万元)",{"id":6,"name":27,"category":28,"favorite":29},"资产评估实务一","会计财税",0]