[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-825655":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},825655,519,1,"单选题","（2018年真题）某在建工程，基础工程已完工，结构工程完工60%，基础，结构和装修占建筑工程总预算的15%，50%和35%，该工程土建部分的完工率为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","39%",false,{"key":16,"text":17,"correct":14},"B","65%",{"key":19,"text":20,"correct":14},"C","75%",{"key":22,"text":23,"correct":24},"D","45%",true,"土建部分的完工率＝15%＋60%×50%＝45%。",{"id":6,"name":27,"category":28,"favorite":29},"资产评估实务一","会计财税",0]