[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-821354":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},821354,516,2,"多选题","下列属于企业提供劳务完工进度的确定，可选用的方法有（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","已完工作的测量",true,{"key":16,"text":17,"correct":14},"B","已提供劳务占劳务总量的比例",{"key":19,"text":20,"correct":14},"C","发生成本占总成本的比例",{"key":22,"text":23,"correct":24},"D","取得的收入占总收入的比例",false,"ABC","企业提供劳务完工进度的确定，可选用的方法包括：已完工作的测量；已提供劳务占劳务总量的比例；发生成本占总成本的比例。",{"id":6,"name":28,"category":29,"favorite":30},"注册会计师-税法","会计财税",0]