[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-812774":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},812774,514,2,"多选题","甲大学与乙公司签订建设工程施工合同，由乙为甲承建新教学楼。经甲同意，乙将主体结构的施工分包给丙公司。后整个教学楼工程验收合格，甲向乙支付了部分工程款，乙未向丙支付工程款。下列表述错误的有（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","乙、丙之间分包合同有效",true,{"key":16,"text":17,"correct":14},"B","甲可以撤销与乙之间的建设工程施工合同",{"key":19,"text":20,"correct":21},"C","丙可以要求乙支付工程款",false,{"key":23,"text":24,"correct":14},"D","丙不得要求乙支付工程款","ABD","本题考核建设工程合同。主体工程分包，分包无效。所以选项A错误。选项B不属于可撤销合同的情形，所以选项B错误。合同无效但验收合格，承包人可以要求参照合同约定支付工程款。所以选项D错误。",{"id":6,"name":28,"category":29,"favorite":30},"注册会计师-经济法","会计财税",0]