[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-811349":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},811349,514,1,"单选题","（2016年）根据合同法律制度的规定，建设工程合同当事人对工程实际竣工日期有争议时，下列处理规则中，正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程竣工验收合格的，以工程转移占有之日为竣工日期",false,{"key":16,"text":17,"correct":14},"B","工程未经竣工验收，发包人擅自使用的，以开始使用之日为竣工日期",{"key":19,"text":20,"correct":14},"C","工程未经竣工验收，发包人擅自使用的，以工程封顶之日为竣工日期",{"key":22,"text":23,"correct":24},"D","承包人已提交竣工验收报告，发包人拖延验收的，以承包人提交验收报告之日为竣工日期",true,"",{"id":6,"name":27,"category":28,"favorite":29},"注册会计师-经济法","会计财税",0]