[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-809837":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},809837,513,2,"多选题","（2014年）甲公司以出包方式建造厂房，建造过程中发生的下列支出中，应计入所建造厂房成本的有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","支付给第三方监理公司的监理费",true,{"key":16,"text":17,"correct":18},"B","为取得土地使用权而缴纳的土地出让金",false,{"key":20,"text":21,"correct":14},"C","建造期间进行试生产发生的负荷联合试车费用",{"key":23,"text":24,"correct":14},"D","建造期间因可预见的不可抗力因素导致暂停施工发生的费用","ACD","选项B，应作为无形资产核算。",{"id":6,"name":28,"category":29,"favorite":30},"注册会计师-会计","会计财税",0]