[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-806202":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},806202,511,1,"单选题","作业成本管理的步骤不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","确认和分析作业",false,{"key":16,"text":17,"correct":14},"B","业绩评价",{"key":19,"text":20,"correct":21},"C","与传统成本计算法比较分析",true,{"key":23,"text":24,"correct":14},"D","报告非增值作业成本","作业成本管理一般包括确认和分析作业、作业链一价值链分析和成本动因分析、业绩评价以及报告非增值作业成本四个步骤。",{"id":6,"name":27,"category":28,"favorite":29},"注册会计师-财务成本管理","会计财税",0]