[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-806034":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},806034,511,1,"单选题","某公司全年（按 360天计）材料采购量预计为 7200吨，假定材料日耗均衡，从订货到送达正常需要 3天，鉴于延迟交货会产生较大损失，公司按照延误天数 2天建立保险储备。不考虑其他因素，材料再订货点为（ ）吨。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","80",false,{"key":16,"text":17,"correct":14},"B","40",{"key":19,"text":20,"correct":14},"C","60",{"key":22,"text":23,"correct":24},"D","100",true,"每日平均需用量 d=全年采购量 \u002F全年天数 =7200\u002F360=20(吨 )。“公司按照延误天数 2天建立保险储备”，所以保险储备量 =2× 20=40(吨 )。再订货点 =平均交货时间 L×每日平均需用量 d+保险储备量 =3× 20+40=100(吨 )。",{"id":6,"name":27,"category":28,"favorite":29},"注册会计师-财务成本管理","会计财税",0]