[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-805693":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":24,"analysis":25},805693,511,2,"多选题","下列关于项目资本成本的说法中，正确的有（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","在使用净现值法评价投资项目时，项目资本成本是“折现率”",true,{"key":16,"text":17,"correct":14},"B","在使用内含报酬率法评价投资项目时，项目资本成本是“取舍率”",{"key":19,"text":20,"correct":14},"C","在使用内含报酬率法评价投资项目时，项目资本成本是“必要报酬率”",{"key":22,"text":23,"correct":14},"D","项目资本成本是项目投资评价的基准","ABCD","评价投资项目最普遍的方法是净现值法和内含报酬率法。采用净现值法的时候，项目资本成本是计算净现值的折现率；采用内含报酬率法时，项目资本成本是其“取舍率”或必要报酬率。因此，项目资本成本是项目投资评价的基准。",{"id":6,"name":27,"category":28,"favorite":29},"注册会计师-财务成本管理","会计财税",0]