[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-805419":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},805419,511,1,"单选题","（2019年）甲公司有X、Y两个项目组，分别承接不同的项目类型，X项目组的资本成本为8%，Y项目组的资本成本为12%，甲公司资本成本为10%，下列项目中，甲公司可以接受的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","报酬率为9%的X类项目",true,{"key":16,"text":17,"correct":18},"B","报酬率为7%的X类项目",false,{"key":20,"text":21,"correct":18},"C","报酬率为10%的Y类项目",{"key":23,"text":24,"correct":18},"D","报酬率为11%的Y类项目","如果投资项目与公司现有资产平均风险不同，公司资本成本不能作为评价标准。此时，评价项目是否接受的标准是该项目的资本成本，即报酬率高于项目资本成本，项目可行。",{"id":6,"name":27,"category":28,"favorite":29},"注册会计师-财务成本管理","会计财税",0]