[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-803508":3},{"question":4,"library":27},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":25,"analysis":26},803508,511,2,"多选题","（2017年）甲公司拟投资一条生产线，该项目投资期限5年，资本成本12%，净现值200万元。下列说法中，正确的有（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目现值指数大于1",true,{"key":16,"text":17,"correct":18},"B","项目会计报酬率大于12%",false,{"key":20,"text":21,"correct":18},"C","项目折现回收期大于5年",{"key":23,"text":24,"correct":14},"D","项目内含报酬率大于12%","AD","对于单一投资项目而言，当净现值大于0时，现值指数大于1，内含报酬率大于项目资本成本，项目是可行的，选项A、D正确；同时，项目净现值大于0，则其未来现金净流量的现值补偿了原始投资额现值后还有剩余，即折现回收期小于项目使用寿命，选项C错误。会计报酬率属于不考虑货币时间价值的静态评价指标，而且是依据会计利润计算的；而净现值、现值指数、内含报酬率、折现回收期均属于考虑货币时间价值的动态评价指标，而且是依据现金净流量计算的。因此，动态评价指标和静态评价指标的结论可能一致也可能不一致，就本题而言，动态评价指标和静态评价指标的结论是不一致的，会计报酬率小于项目资本成本，选项B错误。",{"id":6,"name":28,"category":29,"favorite":30},"注册会计师-财务成本管理","会计财税",0]