[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-798417":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},798417,508,2,"多选题","设备正式安装应具备的条件包括（）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","设备的基础或支架已完成",true,{"key":16,"text":17,"correct":14},"B","安装设备所必须的图纸资料已具备",{"key":19,"text":20,"correct":14},"C","按正常施工程序，设备已运至现场",{"key":22,"text":23,"correct":14},"D","将设备开箱检验完毕、吊装就位并继续进行安装",{"key":25,"text":26,"correct":27},"E","将设备安装到位",false,"ABCD","",{"id":6,"name":31,"category":32,"favorite":33},"(中级) 统计工作实务","会计财税",0]