[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-792948":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},792948,506,1,"单选题","在固定资产投资统计中，建筑安装工程投资额一般按照( )计算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预算价格",true,{"key":16,"text":17,"correct":18},"B","中标价格",false,{"key":20,"text":21,"correct":18},"C","结算价格",{"key":23,"text":24,"correct":18},"D","全部费用","建筑安装工程投资额一般按预算价格计算。预算价格，是在施工图设计时间根据一定时期的预算定额计算出来的工程总费用。由于预算价格是根据一定时期的预算定额和物价水平计算出来的，在工程施工过程中会发生某些价差和量差，因此，应将经建设单位与施工单位双方协商同意的工程价差、量差，视同修改预算价格。建筑安装工程应按修改后的预算价格计算投资完成额。实行招标投标的建安工程，以中标价格作为计算建安工程投资额的价格依据。",{"id":6,"name":27,"category":28,"favorite":29},"(初级) 统计工作实务","会计财税",0]