[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-780470":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},780470,500,1,"单选题","A企业计划投资某项目，该项目全部投资均于建设期开始时一次性投入，投入后立即使用，经营期为8年，投产后每年产生的现金净流量相等。若该项目的静态投资回收期为5年，则该项目的内含报酬率是（ ）。[已知（P\u002F A，12%，8）=4.968，（P\u002F A，10%，8）=5.335]",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","9.38%",false,{"key":16,"text":17,"correct":14},"B","10.58%",{"key":19,"text":20,"correct":21},"C","11.83%",true,{"key":23,"text":24,"correct":14},"D","12.42%","原始投资额=年现金净流量×（P\u002FA，i，8） （P\u002FA，i，8）=原始投资额\u002F年现金净流量=静态投资回收期=5 i=10%+[（5.335-5）\u002F（5.335-4.968）]×（12%-10%）=11.83%。",{"id":6,"name":27,"category":28,"favorite":29},"财务与会计","会计财税",0]